Good News, Bad News

Rain

Good for Lake Lavon

Bad for construction.

Published in: on May 25, 2007 at 10:28 am Comments (0)

Streets and Parking II

Concrete Pour

The last concrete is being poured today for the additional streets and parking. It will be striped for parking spots after VBS (mid-June) but will be open and functional in time for use on Registration Monday!

Previously:
Streets and Parking
Site Plan

Published in: on May 23, 2007 at 10:17 am Comments (0)

Streets and Parking

New Street

By week-end, the concrete and drainage for the new street and parking (the brown shaded area on the site plan) should be complete. This will not only add 150 new parking spaces, but will also provide a much-needed extra exit that meets up with Howell Street for better traffic flow. We might have this complete in time for use at VBS!

Published in: on May 21, 2007 at 5:10 pm Comments (0)

Foundation Work

Rebar

Cages of rebar in deep trenches, preparing for the concrete foundation.